There is no fixed time for the keys. They are released once the buyer's money has reached the seller's conveyancer, and the Law Society's Standard Conditions of Sale, commonly used for home sales in England and Wales, treat money that arrives after 2 pm as late unless the contract sets another time. In a chain, each sale waits for the money from the one below it, so the higher up the chain you are, the later in the day the call tends to come. We plan the removal round that: the van is loaded in the morning and waits, loaded, for the call from your solicitor.

By Duffield Removals. Published 28 November 2026.

Two Duffield Removals Luton vans with their rear doors shut on the gravel drive of a brick house on moving day
Two of our vans on the drive at a house move.

Completion day, in the order it happens

Two things run side by side on completion day: the money, which the conveyancers move, and the furniture, which we move. The furniture only has to wait for the money at the very end, when the keys change hands.

  • We load first. The crew arrives in the time window agreed in your quote, protects the floors and door frames, and loads the house room by room. Under our terms the removal is paid in full, in cleared funds, on or before the morning of the move, so that is settled before the phones start.
  • The buyer's conveyancer sends the purchase money, often by CHAPS, the same-day bank payment that the Bank of England says solicitors and conveyancers commonly use to complete a property purchase.
  • The seller's conveyancer confirms it has arrived, and at that moment the sale has completed. They pay off the seller's mortgage and send the balance on, which is often the money the seller needs for their own purchase further up the chain.
  • The keys are released, usually by the estate agent, once the seller's conveyancer gives the word. Your solicitor rings you, and you ring the crew.
  • We drive to the new house, unload everything where you want it and rebuild any beds we took apart, so the first night is sorted whatever time the keys came.

The 2 pm rule, and why a seller should be loaded early

The Standard Conditions of Sale (fifth edition, 2018 revision) are the Law Society's standard terms, and two of them are about the clock. Condition 6.1.2 says that if the money due on completion arrives after 2 pm, completion is treated as taking place on the next working day when apportionments and compensation for late completion are worked out, as the buyer's default.

Condition 6.1.3 turns that round when a house is sold with vacant possession. If the buyer was ready, able and willing to pay but could not until after 2 pm because the seller had not moved out, the seller is the one treated as in default.

Your contract can set a different time instead of 2 pm, and your solicitor will tell you which applies. For a seller the practical point is the same either way: be loaded and out of the house in good time. It is one reason we load in the morning rather than waiting to hear about the money.

While you wait for the call

The van stays loaded while we wait for the call from your solicitor, within the time we agreed. We allow a one-hour grace period for key delays; after that, waiting time may be charged at the rate set out in your quote, so you know before the day what a long afternoon would cost.

One customer's Google review from December 2025 describes the day as it should go: "Arrived on time, loaded up ready to go as we waited for keys."

If the keys slip to tomorrow

Sometimes the money does not move on the day at all. If the keys slip to the next day or later, the load goes into our storage overnight and we deliver when you have them. The overnight is quoted up front, like the waiting time, so nobody is working out a price on the drive.

If the gap turns into days or weeks, our guide to storage between completion dates explains how the longer arrangement works.

Completion over Christmas and New Year

Completion needs the banks. The Bank of England's CHAPS system is usually open from 6 am to 6 pm, Monday to Friday, and closed on bank and public holidays in England and Wales, and the Standard Conditions do not count weekends or bank holidays as working days either.

Over Christmas 2026 that means no CHAPS on Friday 25 December, Monday 28 December (the substitute day for Boxing Day, which falls on a Saturday) or Friday 1 January 2027, as well as the weekends, so a completion date is very unlikely to be set on any of them. Thursday 24 December and Tuesday 29 to Thursday 31 December are normal working days for the banks.

Booking the van for your completion date

You can book us provisionally before exchange and confirm the day the date is fixed. Our guide on how far ahead to book a removal company explains why Fridays and the last week of the month fill first, and the moving house checklist covers everything in the weeks before, from boxes to meter readings.

When you have a likely date, ask us for a quote for your house move. Our crews work from Chester and from Mid Wales, so see removals in Chester or removals in Mid Wales for the towns we cover from each.

Questions on this

What time do you get the keys on completion day?

There is no set time. The keys are released when the seller's conveyancer confirms the money has arrived. Under the Standard Conditions of Sale, money that arrives after 2 pm counts as late unless the contract sets another time, and in a chain the higher up you are, the later it usually comes.

Can the removal van be loaded before completion?

Yes. We load on the morning of the move while the money is moving, and the van waits loaded for the call from your solicitor. If you are selling, being loaded and out early matters: under the Standard Conditions, a seller who has not moved out by 2 pm can be the one in default.

What happens if completion is delayed on moving day?

The van stays loaded within the time we agreed, with a one-hour grace period for key delays. If the keys slip to the next day or later, the load goes into our storage overnight and we deliver when you have them. Waiting time and an overnight are quoted up front.

When do I pay the removal company?

With us, in full and in cleared funds, on or before the morning of the move. It is in our terms and conditions, and we confirm the booking terms with your quote.

Can completion happen at a weekend or on a bank holiday?

It is very unlikely. CHAPS, the payment system conveyancers commonly use to complete, runs Monday to Friday and is closed on bank holidays in England and Wales, and the Standard Conditions do not count weekends or bank holidays as working days.

How long after exchange is completion?

On the date written into your contract at exchange. If the contract does not give one, the Standard Conditions put completion twenty working days after the date of the contract. Once you have the date, tell us and we confirm the booking.